Past/Future
- Kick-off meeting: Feb 14/2007
- Jun’07: US$ 80k proposal approved by FAPESP for feasibility study
- Reviews:
- Sep’07: CoDR
- Jun’08: PDR
- Dec’08: CDR
- Feb’08: US$ 500k proposal approved by FAPESP
- Mar’08: Prototyping iBTF completed (INPE -> LNA for tests)
- May’08: Preliminary Interface Review @ SOAR
- Jun’08: FEA of instrument structure (Santoro)
- Jun’08: Order detectors and controllers
- Jun’08: Preliminary Design Review
- Dec’08: Critical Design Review
- Apr’09: Begin construction phase
- May’09: Order optics
- Aug’09: Integration, Assembly & Test Phase begins
- Mar’10: Commissioning
- Apr’10: First Light